Sample elemental cost plan

Sample report extract

Elemental estimate for residential planning

This sample shows the presentation style for an elemental cost plan: project information, construction-cost summary, coded element rows, analysis parameters, and review notes.

Construction area180 m2
Current cost excl VATR 2 398 820
Rate per construction m2R 13 326.78
Planning sample only. Final cost depends on drawings, specification, scope, location, site conditions, market conditions, and information quality.

Project reference

SE-SAMPLE-ECP-001

Report status

Sample extract

Estimate base date

Sample base date

Format basis

Elemental cost-control structure

Summary of construction cost

Cost by section

All figures exclude VAT unless noted.

CodeSectionCostCost / m2Cost %
1Primary elementsR 1 853 000R 10 294.4477.25%
2Specialist installationsR 0R 0.000.00%
3EquipmentR 0R 0.000.00%
4Tenant installationsR 0R 0.000.00%
5AlterationsR 0R 0.000.00%
6External works and servicesR 125 000R 694.445.21%
7Price and detail development contingenciesR 98 900R 549.444.12%
8PreliminariesR 207 690R 1 153.838.66%
9Construction contingenciesR 114 230R 634.614.76%
10EscalationR 0R 0.000.00%
11TaxR 0R 0.000.00%

Primary elements

Elemental estimate of construction cost

CodeDescriptionCostQuantityUnitCost / unitCost / m2Cost %
100SubstructureR 238 000180m2R 1 322.22R 1 322.229.92%
101Ground floorR 144 000180m2R 800.00R 800.006.00%
102Structural frameR 0180m2R 0.00R 0.000.00%
103External facadeR 396 000180m2R 2 200.00R 2 200.0016.51%
104RoofsR 216 000180m2R 1 200.00R 1 200.009.00%
105Internal divisionsR 162 000180m2R 900.00R 900.006.75%
106PartitionsR 0180m2R 0.00R 0.000.00%
107Floor finishesR 124 000180m2R 688.89R 688.895.17%
108Internal wall finishesR 92 000180m2R 511.11R 511.113.84%
109Ceiling finishesR 108 000180m2R 600.00R 600.004.50%
110FittingsR 85 000180m2R 472.22R 472.223.54%
111Electrical installationR 158 000180m2R 877.78R 877.786.59%
112PlumbingR 130 000180m2R 722.22R 722.225.42%
113Fire protectionR 0180m2R 0.00R 0.000.00%
114Balustrading handrails etcR 00mR 0.00R 0.000.00%
115Miscellaneous itemsR 0180m2R 0.00R 0.000.00%

Assumptions and exclusions

  • Construction area is used as the common analysis parameter.
  • Element rows are grouped by function so the cost profile can be monitored as information improves.
  • Preliminaries, contingencies, escalation, and tax are shown separately from the primary building elements.
  • Professional fees, statutory charges, finance costs, property costs, and loose furniture are outside this sample construction-cost view.

Next step

Need this for your project?

Send the drawings, scope notes, and preferred turnaround. The estimating team will confirm the suitable package and information requirements.